PCDGPacific Coast Design Group
Active · Pacific Palisades · Rebuild

Returning to Almar

A family's home on North Almar is coming back — measured, engineered, and built to hold for the next fifty years. This is the record of how it happens, week by week.

Slab reinforcement over vapor barrier
July 2026 — slab steel over the vapor barrier, days before the pour
Chapter 01 — February

Starting again, from the ground itself

Before anything rises, the ground has to be made true. The pad was cleared, surveyed, and cut — footings traced into the earth exactly where the engineering says they must sit.

Footing excavation
Excavator cutting pads
Trench grid taking shape
Chapter 02 — The Plan

Every line was drawn before a shovel moved

The rebuild follows a complete architectural and structural set — the house, its hillside section, and a new ADU. These are working drawings, not decoration; they are the same sheets the crews build from.

West and south elevations of the new residence
The house that's coming

A single-level modern home with a raised clerestory roofline and warm wood siding — designed for the way this family actually lives, with an attached ADU alongside.

West and south elevations
Exterior elevations — the house steps with its street
Proposed site plan
Site plan — residence, ADU, and garden court
Building sections
Sections — how the rooms sit within the structure
Chapter 03 — April

Breaking ground

Layout, forms, steel, inspection — then the first concrete arrives. A foundation is poured in hours and lasts for generations; the discipline is in everything that happens before the truck shows up.

Foundation layout
Crew at the footings
Working in the forms
First mixer arriving
First pour

The first mixer on site is a quiet milestone. From here forward, the project is no longer only on paper.

Placement, vibration, finishing — the crew moves in a practiced order while the concrete sets its own schedule.

Placing concrete
Footings poured

“A foundation is poured in hours and judged for decades. We build it like the difference matters — because it does.”

— Frank DiMarco, Founder
Chapter 04 — May – June

Rising from the ground

Form walls climb the slope, steel is tied, and the retaining structure that will hold the hillside takes shape. When the forms strip, the geometry of the house is suddenly legible — rooms you can stand in, edges you can walk.

Form walls
Crew preparing the wall pour
Placing concrete in the forms
Stripped wall
Stepped stem walls
Chapter 05 — July

The foundation holds

Vapor barrier down, slab steel tied, and the last big pour finished under a summer sky. The platform of the house is complete — cured, flat, and ready to carry everything that comes next.

Vapor barrier over the pad
Pump and mixer on the street
Finishing the slab
Finisher at work
Craft

Machines dig and trucks deliver, but a slab is finished by hand — a trowel, a straightedge, and someone who has done it ten thousand times.

Cured slab
Where the build stands

July 2026 — foundation complete. Framing package is next, and the street will see walls before autumn.

Foundation
Phase complete
Framing
Up next
Weekly
Journal updates from site

The project, plainly

StatusActive — foundation complete
LocationPacific Palisades
TypeSingle-family residence with attached ADU
Architectural StyleMid-Century Modern
Construction TypeLike-for-like rebuild
ContractCost-plus GMP — open book
BuilderPacific Coast Design Group — CSLB #1144150 · #1003008
ArchitectUrban Building Workshop, Inc.
Structural EngineerFTF Engineering, Inc.

Every rebuild on this coast starts the same way ours did — with a conversation about what the ground can hold.

Tell Us About Your Project

A confidential inquiry — project type, location, and timeline. We respond within one business day.

Start Here →

Meet With Us

Sit down with our team in the Palisades — or walk an active site with us before any commitment.

Schedule a Visit →

Call Us Direct

Monday–Friday, 7:00 AM – 5:00 PM. After hours, leave a voicemail and we'll return it next morning.

(310) 573-4242 →
More Projects
San Vicente Residence

San Vicente Residence

Just Awarded · Brentwood
Carbon Beach Residence

Carbon Beach Residence

Completed · Malibu
Bella Oceano

Bella Oceano

Completed · Pacific Palisades
Casale

Casale

Completed · Pacific Palisades
View All Projects →